Natural gas station

Anyone planning a new building in New York City (NYC), or enlarging the gas service for an existing building, needs to apply for a new gas service. Anyone planning to convert an oil-burning boiler to one that is fired by natural gas will also need to apply for a new gas service. NY Engineers is the best gas service provider for a building still to be constructed or new gas service for an existing building. We also offer a flat price which will save you money and enable you to budget accurately.

Need help?

Keith Fink

Principal

(786) 788-0295

inquiry@ny-engineers.com

Get In Touch

Why Choose Us?

We are one of the fastest growing MEP design firms in the construction industry. We pride ourselves on having a fast turnaround while providing cost effective solutions. We are licensed in 50 states and are your one stop shop for all MEP design needs.

0

States

We are licensed in all 50 states!

0

Errors

We design to the perfection

0

Days

Enjoy our lightening fast turnaround

0

Projects

We have completed so far!

0

First Time Approval

Our designs are approved by DOB in one go

0

Repeat Customers

The best service experience in the market

Get Pricing On a New MEP Design Proposal in Fewer than 24 Hours

Request a proposal

Natural Gas Service Providers

Gas Utilities In NYC

Natural gas currently fuels a significant percentage of cooking needs and about 65% of heating requirements in New York City (NYC) buildings. Additionally, it fuels almost all (more than 98%) of in-city electricity produced by power plants. Between 2005 and 2013, U.S. natural gas production increased at an unprecedented 33% across the board.

In 2016, the New York State Code Council updated both the commercial and residential provisions of the State’s Energy Code that are based on the International Energy Code 2015.  

Con Edison owns and operates the gas distribution system in the Bronx, Manhattan, and parts of Northern Queens. National Grid owns and operates the rest of the City’s system including Upstate NY, Rhode Island, and Long Island. These two utility companies alone are authorized to deliver energy in the form of natural gas. However, once the gas service has been installed, consumers may choose any approved energy service company (ESCO) to provide the supply. So, if we do your gas piping design and installation, we deal with the relevant utility company, depending on where you live or where your building is located. You then decide which energy service company you will buy gas from.

The way the system works is that there are privately-owned interstate pipelines that transport natural gas from the Gulf Coast in Western Canada, Texas, and other points of production to interconnection points known as City gates. It then enters the NYC facilities system from where it is drawn at high pressure and piped to power plant facilities that generate electricity, as well as to steam plants. Gas is also piped to hundreds of district regulator stations where the pressure is reduced before it is sent into a vast network of underground distribution mains.

The original gas infrastructure of all U.S. cities comprised low-pressure pipework made of bare steel and cast iron. The modernized system mains are made of coated steel and plastic that can accommodate a high-pressure system and are considerably more efficient. Operators of the gas system have gradually been replacing the outdated portion of the mains and upgrading it to a high-pressure system.

In a report titled A Stronger, More Resilient New York, released by NYC in 2013, comprehensive, actionable recommendations were laid out in an attempt to increase the resilience of buildings and infrastructure. Recognizing that the demand for natural gas peaks on cold, winter days, the two utilities ask large users and plants generating electricity from natural gas to switch to liquid fuels. This is simply because the capacity of the interstate pipelines can exceed demand.

As the report points out, new pipeline connections for NYC represent significant advances in the City’s initiatives towards cleaner burning fuels – specifically oil versus natural gas.

Con Edison & National Grid

As mentioned above, the two utility companies that service New York are Con Edison and National Grid. We have substantial experience dealing with both companies.

Con Edison has a number of different business segments including Consolidated Edison Company of New York (CECONY), a regulated gas, electric, and steam utility company. It’s biggest revenue is electricity, with 3.3 million customers, and gas trailing behind with about 1.1 million customers, but ahead of its income from steam services which are available in Manhattan below 96thStreet.

Orange & Rockland Utilities (O&R) is a much smaller entity providing southeastern New York, northern New Jersey, and eastern Pennsylvania with electric services and southeastern New York and eastern Pennsylvania with gas services.

Con Edison Solutions is an ESCO that has a number of sustainability initiatives and is recognized as the number two solar energy producer in North America.

Con Edison Transmission (CET) invests in both natural gas and electric transmission projects that are able to offer customers access to a surprisingly diverse selection of low-cost energy supplies.

National Grid is a British company that also operates in New York, Rhode Island, and Massachusetts. The company operates systems that deliver natural gas and electricity.

The company has stated its intention to strive for a decarbonized energy infrastructure in the U.S. and has set 2050 as its target year, in line with the commitment of the states it operates in to significantly reduce greenhouse gases by this time. Part of the company’s mission is to continue persuading home and business owners to switch from oil to natural gas, a process we are able to facilitate. Another is to reduce methane emissions and, in this way, make natural gas a cleaner transition fuel.

Gas Service Facts

Planning A New Gas Service

Anyone planning a new building in New York City (NYC), or enlarging the gas service for an existing building, needs to apply for a new gas service. Anyone planning to convert an oil-burning boiler to one that is fired by natural gas will also need to apply for a new gas service.

There are three categories of building for new gas service in NYC:

  1. residential one to five family buildings
  2. multifamily units for more than six families
  3. commercial buildings

Specifications in codes do vary from one to the other. For example, there are possible waivers for large dwellings, commercial and mixed-use buildings for gas meters to be located inside rather than outdoors.

There are two utility companies that own the gas distribution system and service NYC, Con Edison and National Grid. Con Edison supplies the Bronx, Manhattan, and parts of Queens (northeast and Astoria) while National Grid supplies most of Queens, Brooklyn, and Staten Island. As mentioned above, while you will have to apply to one or other of these utility companies for installation of a new gas service in New York, once you are connected you can choose whether to buy your gas from this company or another natural gas provider or ESCO.

Before the application for a new gas service can be made, a professional engineering firm will need to perform a detailed survey of the site to ascertain gas load requirements and other details. You will also need a gas piping design that complies with local codes and other relevant legislation. This will specify all the important design elements including the size of pipes to be used for the gas piping system and the supply pressure.

Whether you need a new gas service for a building still to be constructed or new gas service for an existing building, it New York Engineers offers the fastest average turnaround time from the moment we are hired to approval. We also offer a flat price which will save you money and enable you to budget accurately.

Application For A New Gas Service

Pressure meters on natural gas pipeline for new gas service

It may sound obvious, but before applying for a new gas service it is essential to establish whether a gas service is available in your area. Unfortunately, the type and size of gas service requested are not always available. Having established that a new gas service is available, it is essential to apply as far in advance as possible so that all engineering and construction details can be organized in anticipation of the completion date required.

Before any application for a new gas service can be processed, utility companies require customers to complete a gas load letter to provide precise information regarding the new gas equipment to be installed. The gas load letter also formalizes the terms and conditions of the agreement as well as the commitment of customers to pay bills and agree to indemnify the utility company in various circumstances.

While the gas load letters different utility companies require customers to complete vary, basic information required includes the:

  • Type of equipment to be used for heating, cooking, powering air conditioners and the whole spectrum of appliances that might be used.
  • AFUE (Annual Fuel Utilization Efficiency) that is a measure of how efficiently boilers and furnaces utilize fuel, and which is presented as a percentage of how much fuel (in this case natural gas) it can convert into usable heat. Any figure under 100% is lost.
  • Number of items (quantity) to be included in the gas service system.
  • Model of the items of equipment and appliances that will run off gas.
  • Pressure of the gas to be used to operate each piece of equipment or appliance.
  • BTU (British thermal unit) input for each piece of equipment as well as the total BTU input. The BTU is the traditional non-metric unit of heat needed to raise the temperature of a pound of water from about 39.2 °F by one degree. It is more commonly used in the U.S. than in Britain!
  • Rate at which the gas will be charged, namely either firm or dual fuel, and possibly interruptible if customers agree to burn oil when required to by the utility company.

Energy efficiency is also important, so the gas load letter often asks whether there will be pipe insulation, as well as roof and wall insulation, building controls and so on.

In addition to the gas load letter, Con Edison requires customers applying for a new gas service to sign a standard “hold harmless” agreement which indemnifies the company, employees, agents, affiliates, and so on from liabilities, damages, losses, and anything else that might arise should something go wrong.

Once the application has been received by the utility company they will assess the application and, amongst other things, determine whether the loads required will be adequate. If accepted, excavation and installation of gas service will be initiated in accordance with approved engineering layouts and plans.

Installation Of A New Gas Service

Installation of all new gas services in the U.S. must be carried out in accordance with the 2018 International Fuel Gas Code (IFGC) in addition to any local laws and codes that are applicable. They are usually quite similar although local laws and codes are more specific. For instance, while the Fuel Gas Code of New York State (NYS) is, in essence, the same as the IFGC there are a number of state amendments.

NYC also has relatively new local laws designed to increase safety and minimize risks caused by the aging NYC gas piping infrastructure, including explosions. For instance, the NYC Local Law 159 of 2016 was introduced to try and stop dangerous violations relating to gas piping systems.

  • It is now illegal to install, add to, alter, repair, remove, or replace gas, mechanical, or plumbing systems without a valid application and permit.
  • It is unlawful to connect gas until a certificate of approval has been received from the Department of Buildings (DOB).
  • Once new gas service piping has been installed, it must be locked-off by the utility company and the lock may not be removed until the gas distribution and meter piping has been inspected and certified by the DOB.
  • It is illegal to operate or alter a newly installed gas system without notifying the utility.
  • Owners must notify the utility company when shutoff of gas flow is required for alterations, extensions, or repairs.
  • Gas piping systems must be checked for possible leakage immediately a gas system has been turned on after a shutoff. If there is still a leak the gas supply must be shut off again until all the necessary repairs have been made.

The actual installation process concerns various utility company departments. Gas Operations or Construction Management might oversee third-party contractors that work for the utility, while Gas Operations will usually install company-owned facilities including mains, services, and set-up of gas regulators. Customer Operations will deal with accounts and payments and everything related to these.

Once the installation is complete, customers contact Energy Services or the gas conversion representative to schedule a final inspection. If everything is in order, the utility will set the meters and turn on the gas service.

Have an MEP Engineering Project? Talk To Us.