How MEP Engineering Reduced Rooftop Equipment by 67% for a 3,500 sq. ft. Escape Room Facility

INDUSTRY

Commercial Entertainment

LOCATION

North Carolina

PROJECT SIZE

3,500 sq. ft.

PROJECT TYPE

Brownfield

SERVICES

Full MEP Design

TIMELINE

2 Weeks

Project Overview

A 3,500 sq. ft. Escapology entertainment center in North Carolina was being developed within an existing building, with each escape room designed around a different theme and experience.

Unlike a conventional commercial fit-out, each room had its own combination of lighting, power, low-voltage, audio, access-control, and mechanical requirements, all within a tightly coordinated space.

The project also needed to make use of the building's existing HVAC infrastructure while accommodating equipment requirements established by the games vendor.

The challenge was to develop a coordinated MEP design that could support multiple themed environments, work within the existing building, and be delivered within an accelerated two-week timeline.

The Challenge

The existing building and specialized entertainment requirements created several coordination challenges.

The design needed to:

  • Accommodate different power, lighting, low-voltage, audio, and control requirements across each escape room
  • Integrate game equipment and systems specified by the games vendor
  • Evaluate whether the existing three rooftop units (RTUs) were actually required
  • Coordinate access-control and door systems with the fire alarm system
  • Address field conditions where the installed electrical work differed from the approved design

The analysis needed to consider the facility as an integrated system rather than treating each themed room or building system independently.

The MEP Engineering Approach

Engineering Each Room Around Its Experience

Each escape room had its own combination of equipment and systems, requiring the MEP design to account for the specific experience planned for that space.

Requirements for specialty lighting, speakers, equipment, low-voltage systems, and access controls were coordinated with the games vendor before being integrated into the electrical and low-voltage layouts.

This allowed room-specific systems to function as intended while maintaining coordination across the facility.

Reducing Three RTUs to One Through Load Analysis

The client initially wanted to reuse the building's three existing RTUs.

Rather than assuming all three units were required, airflow balancing and occupancy calculations were used to evaluate the facility's actual HVAC requirements.

The analysis showed that one RTU could satisfy the facility's requirements, reducing the rooftop equipment requirement from three units to one.

This resulted in a 67% reduction in rooftop equipment while meeting the facility's ventilation requirements.

Coordinating Access Control With Fire Alarm

The facility's entertainment technology introduced additional life-safety coordination requirements.

Motion sensors and access-control systems were coordinated with the fire alarm system so that required doors could unlock during a fire alarm event.

This allowed the entertainment and life-safety systems to operate together rather than as independent installations.

Resolving Field Conditions During Construction

During inspection, the installed electrical work was found to differ from the approved drawings, including outlet faceplates that had not been installed as specified.

The discrepancy created draft- and fire-stopping concerns and required coordination during construction.

The issue was reviewed with the contractor and reviewer to identify the required correction and bring the installation back into alignment with the approved design and applicable requirements.

Project Outcomes

The coordinated MEP approach allowed the facility to accommodate its specialized entertainment requirements while making effective use of the existing building infrastructure.

  • 67% reduction in rooftop equipment, reducing the requirement from three RTUs to one while meeting the facility's ventilation requirements
  • 2-week delivery, with the coordinated MEP design completed within the accelerated project timeline
  • First-submission approval, with the permit package approved without an additional submission cycle
  • Multiple themed environments, one coordinated system, integrating room-specific power, lighting, low-voltage, audio, and access-control requirements
  • Construction issue resolved, with field discrepancies addressed through coordination with the contractor and reviewer

Project Journey

01

Initial Design: Coordinated with the client and games vendor to establish the unique power, lighting, low-voltage, audio, access-control, and mechanical requirements for each themed escape room.

02

First Submission: Delivered the first coordinated check set, integrating vendor-specific requirements while maintaining coordination across the engineering disciplines.

03

Permit Approval: The permit package was approved on the first submission, avoiding an additional permitting cycle.

04

Construction Support: Engineering support continued during construction after an inspection identified discrepancies between the installed electrical work and the approved drawings.

05

Field Resolution: The installation issue was addressed through coordination with the contractor and reviewer to restore alignment with the approved design and applicable requirements.

Planning an entertainment or commercial fit-out within an existing building?

Entertainment spaces can bring together highly specialized requirements that don't exist in a typical commercial fit-out.

Frequently Asked Questions

What MEP systems were required for the escape room facility?

The design incorporated power, specialty lighting, low-voltage systems, audio, access control, HVAC, and life-safety coordination to support the different themed environments.

Why were three RTUs reduced to one?

The existing RTUs were evaluated using airflow balancing and occupancy calculations. The analysis showed that one RTU could satisfy the facility's requirements.

What was the result of the HVAC analysis?

The rooftop equipment requirement was reduced from three RTUs to one, representing a 67% reduction in rooftop equipment.

How were the escape room systems coordinated?

Game equipment and technical requirements were coordinated with the games vendor before being integrated into the electrical and low-voltage layouts.

How quickly was the project delivered?

The coordinated MEP design was completed within a two-week timeline, with the permit package approved on the first submission.