In an effort to mitigate a potential gas utility shutdown, this engineering case study has been generated. This study will focus on the types of information and data necessary to ensure the completeness for each section of the project application, affecting engineering feasibility. The below points demonstrate the importance of this review:
Scope of Work
Cost Estimate
conEd shut down gas service for the entire building in this particular project. It was our goal at NY Engineers (NYE) to get the client's gas service restored as soon as possible. In conjunction with contractor oversight, NYE prepared drawings and filings to get this problem solved quickly.
The end goal was to restore building gas service to Hudson View Gardens, Building G, a 30,000 square feet residential building. This building consisted of 24 apartment units. Engineering plans were prepared and filed with the New York City Department of Buildings (NYC DOB) in order to conduct repairs and restore the aging gas piping infrastructure.
The apartment building demonstrated signs of a gas leak due to its aging piping infrastructure. To prevent any future catastrophe due to the hazardous nature of gas, the utility company conEd who services the building, shut down the gas service until repairs were completed and the building demonstrated no further leaks.
With the gas shut down in effect, this left the 24 apartment units with no gas for cooking, which led to a lot of upset tenants. Adding to the complexity of the project, each apartment had a separate meter which implies 24 gas risers. This meant each riser had to be tested for gas leaks and repaired, if necessary. A full passing pressure test of all gas piping was required for gas service to be restored.
Engage an Engineering Firm (NY Engineers) to create an engineered solution to repair and restore the gas service for the building. Any construction required to repair/replace gas piping must be filed with the NYC DOB and must be communicated to conEdison. This requires a licensed Professional Engineer to produce engineering drawings for filing and interface with the utility department.
Building G, along with its infrastructure, was constructed in 1925. The gas system was poorly maintained and the pipes began to deteriorate with age. During a field survey, it was found that the meters were locked due to conEd shutdown, determining that all shutoff valves were likely to be replaced, which they were.
Estimated cost to replace necessary piping and valves: $2,700
Engineering cost for drawing preparation and filing: $17,000
Construction cost:$68,000
1. conEd shutdown
2. Engineering survey/strategy
3. Prepare/file engineering plans
4. Pressure testing/leak finding
5. Passing pressure test
6. As-built drawings/sign off
7. As-built drawings/sign off